Andhra Pradesh High Court rules withholding admitted contractor payments breaches constitutional rights
Originally reported by Taxguru as: Corporate Law | Non-Payment of Contractor’s Admitted Dues Violates Article 21: Andhra Pradesh HC
25 Nov 2026, 12:15 pm IST · Xecute.finance News Desk
The crisp read
The Andhra Pradesh High Court held that withholding undisputed dues for completed government projects violates Article 21 of the Constitution. It ordered authorities to release an outstanding sum of Rs. 15,92,859 with 12% annual interest from the bill submission date. The case involved an agreement valued at Rs. 23,19,566 for constructing a BC Boys building in Nellore District.
Xecute Impact Breakdown
For CAs
- Professionals handling government contracts can advise clients that withholding admitted dues for completed infrastructure projects is illegal and violates Article 21.
- Advise aggrieved contractors to approach the High Court under public law remedies to recover outstanding amounts along with interest.
- Note that the Andhra Pradesh High Court mandated payment of the outstanding amount along with 12% per annum interest from the bill submission date.
For businesses
- Contractors executing government projects can legally challenge the non-payment of admitted dues caused by fund shortages in the Comprehensive Financial Management System.
- Businesses are entitled to recover their outstanding bill amounts along with interest at 12% per annum starting from the date the bill was submitted.
- In this case, the Andhra Pradesh High Court ordered the payment of Rs. 15,92,859 for a completed BC Boys building project in Nellore District.
Deep dive – the full story
The Andhra Pradesh High Court ruled in Kathupalli Venkata Sowmya Vs State of Andhra Pradesh that retaining legitimate dues owed to a contractor for completed government infrastructure projects is arbitrary, illegal, and violates Article 21 of the Constitution of India. The Court mandated respondents to pay the outstanding amount of Rs. 15,92,859 along with interest at 12% per annum starting from the date the bill was submitted. The petitioner successfully bid on a tender floated by the Andhra Pradesh Education and Welfare Infrastructure Development Corporation (APEWIDC) to complete an incomplete BC Boys building located at Venkatagiri in Nellore District, signing an agreement on 9 November 2017 for a contract value of Rs. 23,19,566. After finishing the construction, the second and final bill totaling Rs.
15,92,859 was cleared on 8 February 2019, but funds were withheld despite the user department admitting the work was completed and handed over, after accounting for gross bill claims of Rs. 17,11,967 and recoveries of Rs. 1,19,108. The executing agency cited fund shortages through the Comprehensive Financial Management System as the reason for non-payment. Public law establishes that state bodies cannot withhold undisputed payments for executed works citing internal budgetary constraints. Constitutional protections guarantee that the right to livelihood and property cannot be infringed upon by arbitrary executive inaction, shifting the legal position from passive endurance of delayed state payments to enforceable constitutional remedies. Contractors who complete public works retain a legally enforceable right to timely financial compensation once bills are passed and approved by the executing department.
Contractors facing delayed dues should gather all completion certificates, approved bills, and correspondence with executing agencies to pursue legal remedies in high courts. Professionals advising infrastructure clients must track CFMS processing records and prepare writ petitions invoking constitutional provisions when administrative delays persist. Bottom line: government bodies must clear admitted contractor dues promptly or face court-mandated interest payments for violating constitutional guarantees.
Source: taxguru.in
This is news/educational content, not investment advice. Xecute.finance is not SEBI-registered. Consult a qualified professional before acting.
More from the Xecute news desk
- Supreme Court rules petroleum dealership arbitrator cannot alter separate lease terms or rent
- Delhi High Court affirms Section 34 courts cannot reappreciate evidence to overturn arbitral awards
- Delhi High Court rules written statement filed within 120 days without admission affidavit is valid
- Amazon expands digital vehicle marketplace internationally with scheduled United Kingdom launch in early 2027
Reading the static edition.
The live app adds Ask Xecute, deadline trackers, the daily quiz and one-tap deep dives.
Open this story in the Xecute app →